The Overhead Equipment (OHE) system has been energised on the 50 km long Surat-Bilimora section under the Mumbai-Ahmedabad High-Speed Rail Corridor Project on November 20, 2026. This will pave the way for testing activities for the project. The section includes both Up and Down lines on the elevated alignment along with bridges across four rivers and a steel bridge over National Highway 53 (NH-53). 

Besides, the first Traction Substation (TSS) at Bilimora has completed installation works in the control panel, changeover switch, transformer and circuit breaker buildings. Moreover, the TSS in Gujarat will receive power from the 220 kV Ambetha grid substation of Gujarat Energy Transmission Corporation Limited (GETCO).

The project involves development of a 508.17 km long Mumbai-Ahmedabad high speed rail (HSR) corridor in the states of Maharashtra and Gujarat, equipped with an advanced 2×25 kV overhead traction system and 14 TSS. It is being implemented by a special purpose vehicle (SPV), named National High Speed Rail Corporation Limited (NHSRCL), incorporated by the Ministry of Railways (MoR) and the respective state governments of Maharashtra and Gujarat with an equity stake of 50:25:25 respectively. The project is India’s first high speed rail corridor and also includes a 21 km long tunnel, including a 7 km undersea stretch, from Mumbai to Thane. The revised estimated cost of the project is Rs 2,027.97 billion.