As of August 31, 2026, a total of 16 out of 19 zones have achieved 100 per cent electrification, while the progress on the remaining zones is as follows:

S NoZoneTotal BG RKMElectrified upto 31.08.2026% Electrified 
1SECR           2,485           2,485100%
2NR           7,601           7,601100%
3NER           3,244           3,244100%
4WCR           3,249           3,249100%
5NCR           4,425           4,425100%
6ECoR           2,597           2,597100%
7CR           4,070           4,070100%
8ER           2,832           2,832100%
9KRCL           738           738100%
10Metro            50            50100%
11SER           2,753           2,753100%
12ECR           4,460           4,460100%
13SCR           3,175           3,175100%
14WR           6,202           6,202100%
15NWR           6,204           6,204100%
16SCoR 3,532 3,532100%
17SWR 3,469 3,33396.1%
18SR           5,068           5,00098.7%
19NFR           4,274           4,21998.7%
 TOTAL         70,428         70,16999.6%

                                                                                        Source: Indian Railways